Taabi

Businesses · Infrastructure

Most of the fleet isn't yours.
All of the cost is.

For infrastructure teams running multi-year packages across corridors, spans and stretches — usually with more vendor equipment on site than their own.

Measured in
₹ / asset-month
What each asset costs the package carrying it.
Assets in scope
Owned + vendor
Ownership is split. The cost sheet is not.
Margin on ₹100
₹8
On a package measured in years.
Contested
₹78
Hire, diesel and standby — all settled by argument.

The drain

Follow one hundred rupees of package value down a single asset-month.

On an infrastructure package, the largest line in equipment cost is a bill from somebody else — raised against hours you did not record, for diesel you did issue, on a machine you cannot switch off.

₹100 EARNED
Margin Left
₹100/ asset-month
Left of ₹100 of value− ₹0 spent
Cost 01 · The vendor−₹40

Forty rupees, billed against a reading you did not take.

The largest single line in equipment cost is an invoice raised by the counterparty, certified by you, and supported by an hour meter that only one of the two parties has ever looked at.

Visible today
The invoice is arithmetically correct.
Blind spot
The number it multiplies was supplied by the party being paid.
Cost 02 · Your fuel−₹24

Your diesel. Their machine. Whose package?

On most packages the principal contractor issues the fuel and the vendor operates the plant. Between the yard and the engine there is no record, and shared assets move between packages without one.

Visible today
The bowser slip is signed.
Blind spot
Which asset drew it, and for which package, is unrecorded.
Cost 03 · Doing nothing−₹14

The most expensive asset on the package is the one doing nothing.

Standby is contractual, legitimate and almost never examined. An asset mobilised early, or held after its scope closed, bills exactly the same as one that is working.

Visible today
Standby is claimable under the contract.
Blind spot
Whether it was avoidable is a question nobody can answer.
Cost 04 · Wear−₹9

Small, until it lands on the critical path.

Nine rupees of maintenance is not the risk. The risk is a stalled asset on a milestone activity, where the cost is not a repair but a penalty and a stretch of schedule.

Visible today
Repair cost is exact and modest.
Blind spot
The schedule cost behind it is neither.
Cost 05 · Movement−₹5

Paid once. Charged to whichever package is easiest.

Assets move between stretches and packages across a build that runs for years. Mobilisation lands on a cost centre chosen by convenience, not by consumption.

Visible today
The cost is known.
Blind spot
The package it belongs to often is not.
What's left₹8 left

Eight rupees. And seventy-eight of the ninety-two that took it are settled by argument.

Hire, diesel and standby are ₹78 of every ₹100 — and every one of them is contested at the point of invoice, which is precisely the moment at which nobody has a record. Instrumentation moves that argument backwards, to the hour it actually happened.

Visible today
Margin per ₹100 of package value: ₹8.
Blind spot
Contested cost per ₹100: ₹78. Nearly ten times the margin.

One package month

You control the cost. Somebody else controls the record.

A single month on a live package. Five moments where equipment cost is created — and in four of them the only witness works for the vendor.

This is not an allegation of bad faith. It is a measurement gap, and it closes the moment an independent record exists.

01 — MOBILISE

The plant arrives. So does the standby clock.

Two crawler cranes mobilised for a span erection that slipped six weeks. The contract entitles the vendor to standby, and they took it — correctly, and without anyone noticing until the bill.

Mobilisation logStandby detectionContract-linked
2 × crawler crane · Package 390 days on hire
41 days
On standby, zero engine hours. Contractual, legitimate, and entirely avoidable.
41 days Standby · erection deferred
38 days Working · span erection
11 days Demobilisation

Avoidable, if anyone had been watching the front and the mobilisation date at the same time. Nobody was, because they sit in two different systems.

02 — DEPLOY

Which package is this machine on today?

Shared plant crosses from Package 3 to Package 5 and back. Cost follows whoever raises the invoice first, not whoever consumed the asset. On a multi-year build, this is the largest source of misattributed equipment cost.

Package geofencesCross-package movementCost attribution
EX-91 · March hoursBilled to Package 3
74 hours
Package 5's work, sitting on Package 3's cost sheet. Nobody committed a fraud.

There was simply no boundary that could tell. On a four-year build with shared plant, this is the largest single source of misattributed equipment cost.

03 — DRAW

You issue the fuel. They operate the machine.

The bowser slip records a quantity and a signature. It does not record which asset the diesel entered, or whether the hours claimed against it could have consumed that much.

Bowser reconciliationAsset-level drawFuel vs hours check
Diesel gap · issued minus receivedCumulative · Package 3 · March
1,220 litres
Unaccounted across one package, in one month. ₹1.16 lakh, on one cost sheet.
300 L 600 L 900 L 1,200 L Mid-month · 560 L Month close MARCH · PACKAGE 3

At mid-month it is a rounding difference nobody would raise. Over a four-year build across a dozen packages, it stops being a rounding difference and starts being a budget.

04 — STANDBY

Idle plant invoices exactly like working plant.

Eleven vendor assets on the package. Three have not recorded a working hour in nineteen days. All eleven appear on the monthly bill at the same rate.

Utilisation by vendorIdle rental registerRelease recommendations
Vendor plant · hours under load% utilisation, by week
6%
Vendor C plant, hours under load. All three vendors bill against the same rate card.
WEEK 1WEEK 2WEEK 3WEEK 4
Vendor A · 6 assets
Vendor B · 2 assets
Vendor C · 3 assets
IDLE WORKING

Three vendors, one rate card, a threefold difference in what the package actually received. Until it was measured, all three were simply 'on site'.

05 — CERTIFY

You certify what you could not witness.

Every month, a commercial team signs off hire charges, diesel and standby against readings supplied by the party being paid. Not because they are careless, but because there has never been an alternative record.

Independent hour recordInvoice reconciliationPackage cost roll-up
Certification · Package 3 · March11 assets, reconciled
₹22.4 lakh
Settled before the payment left, rather than disputed after it.
CLAIMED Vendor hire bill, 11 assets₹94.2 LInvoice
RECORDED Telemetry hours, geofenced to package₹71.8 LTaabi
SETTLED Reconciled before payment, not after₹22.4 LRecovered

The dispute did not go away. It simply moved to before the payment — which is the only side of it where it can still be won.

How Taabi is different

An invoice is not certifiable until it survives five checks.

Every vendor can supply an hour meter reading. That is a claim, and a claim from the party being paid is a negotiation.

Taabi holds the claim against hour meter, engine load, package geofence, fuel draw and vendor pattern before a commercial team is asked to sign it.

Under examination
₹94.2 L
Package 3 · vendor hire bill · March · 11 assets
Illustrative exception · representative package
01
Hour-meter telemetry
Hours are recorded continuously, by you.

A monthly reading supplied at invoice can only be accepted or contested. A continuous record is not a counter-claim — it is simply what happened, and it existed before the argument did.

Rules out retrospective reading
02
Engine load & OBD
The plant ran. Six per cent of it was under load.

Standby, warm idle and working hours are three different things billed at one rate. Engine load is the only signal that separates them, and no hour meter carries it.

Rules out idle billed as work
03
Package geofence
Seventy-four hours were spent on Package 5.

Shared plant crosses boundaries. Without a geofence, cost lands on whichever package raised the invoice first — which on a multi-year build compounds into a number nobody can unwind.

Rules out cross-package billing
04
Fuel draw
The diesel consumed cannot support the hours claimed.

An excavator under load burns at a knowable rate. If the claimed hours had been worked, the fuel would show it. Fuel is the physical check that an hour meter cannot be argued past.

Rules out phantom hours
05
Vendor pattern
This vendor bills 31% above their own telemetry, every month.

One month is a discrepancy. Six is a commercial position — and it moves the conversation from a disputed invoice to a renegotiated rate, at the next award rather than at the next argument.

Establishes pattern
Verdict · reconciled

₹22.4 L, settled before payment. The certification stops being an act of trust.

The five signals are not a feature list. They are the reason a commercial team can sign the bill and defend it — and the reason the conversation happens before the money moves, not after.

This is the whole difference. A vendor's hour meter gives you a claim. Hour meter plus load plus geofence plus fuel plus pattern gives you a record — and only a record can be certified.

Use cases

Where infrastructure teams start.

Business impact

What changes.

Not a percentage we cannot source. A list of things that are true on the left today, and true on the right after.

Vendor hours are taken on trust
Vendor hours are independently recorded
Diesel crosses packages untraced
Diesel is attributed to asset and package
Idle vendor plant invoices anyway
Idle vendor plant is visible, and challengeable
A critical-path asset fails unannounced
Failure risk is flagged against the milestone
Package cost is reconstructed afterwards
Package cost accrues in the open
The bill is disputed after payment
The bill is reconciled before it

Every row on the right resolves to the same denominator — ₹ / asset-month

Proof slot — empty

One named infrastructure customer, with fleet or asset count and a measured delta. This is the block an enterprise buyer scans for evidence, and it is the one thing this page does not yet have. Fill it with a customer — not a borrowed benchmark.

Who it's for

Built for the teams carrying the number.

Project directors

The milestone is the only currency

Leaders whose penalty exposure is measured in weeks, and whose equipment risk is measured in nothing.

Commercial and QS

You certify what you cannot verify

Teams signing hire bills and diesel consumption on readings taken by the counterparty.

Vendor management

Two vendors, one rate, different value

Managers who cannot separate the vendor whose plant runs from the vendor whose plant is merely present.

FAQ

Infrastructure, answered.

What is vendor fleet intelligence in infrastructure?

It is an independent record of what every asset on a package actually did, regardless of who owns it. Engine hours, diesel drawn, idle time and location are recorded at the machine and attributed to the package carrying the cost, so hire bills, diesel and standby claims are reconciled against measurement rather than settled by negotiation at the point of invoice.

Why is vendor equipment the biggest cost risk on a package?

Because it inverts the usual relationship between control and exposure. You carry the cost, the schedule risk and, on a live corridor, the reputational risk — while the party operating the asset also supplies the record you are billed against. That is not an allegation of bad faith; it is a measurement gap, and it closes the moment an independent record exists.

Will vendors agree to have their equipment instrumented?

In practice this is a contracting question more than a technology one, and it is easiest to resolve at award rather than mid-package. Vendors whose plant genuinely runs tend to be indifferent or supportive, because an independent record settles standby and idle disputes in both directions. Resistance is itself informative, and worth surfacing before mobilisation rather than after.

Get started

Move from tracking the assets you own, to accounting for every asset on the package.

See the drain, the package month and the evidence chain run across owned, hired and vendor plant on one view.